According to 1M AI News monitoring, Natarajan Ramachandran, Director of Product Marketing for Broadcom's Physical Layer Products Division, stated that TSMC's production capacity is reaching its limit, saying, "A few years ago, I would have said its capacity is unlimited." He mentioned that TSMC plans to expand its capacity by 2027, but the 2026 capacity bottleneck has already "clogged the supply chain."
The shortage has spread beyond semiconductors. Ramachandran noted a significant supply constraint in the laser sector, with PCBs (printed circuit boards) becoming an "unexpected" bottleneck, causing PCB lead times for optical transceivers to stretch from about 6 weeks to 6 months. PCB suppliers in Taiwan and mainland China are facing capacity limits. Many customers are now signing 3- to 4-year long-term agreements with suppliers to secure capacity, with Samsung Electronics also stating last week that they are moving towards 3- to 5-year agreements with key customers.